- OBJECTIVE:
To describe a procedure for the preventive maintenance of Sampling &Dispensing Booth.
SCOPE:
This SOP is applicable for preventive maintenance of Sampling & Dispensing Booth
Assistant Engineer/Above shall be responsible for implementation and compliance of the SOP.
ACCOUNTABILITY:
Manager-Engineering / Manager-Production / Head-QA shall be accountable for implementation and
Compliance the procedure mentioned in this SOP.
ATTACHMENT:
Preventive Maintenance Checklist of Sampling & Dispensing Booth – Attachment – I
PROCEDURE:
- Preparation of preventive maintenance plan:
- Inform the concern person before starting preventive maintenance.
- Ensure that no activities are carried out in the respective machine.
- Ensure that the respective system electrical supply is switched “OFF”
- Before carrying out the preventive maintenance display status board as “UNDER PREVENTIVE
MAINTENANCE” on the electrical panel and machine.
- FREQUENCY:
- Quarterly
- CHECKLIST:
- Check the electrical terminals of main supply and machine.
- Check and ensure the free rotation of the blower motor shaft. Lubricate bearings, if required
- Clean the impeller and its scrolls.
- Clean the whole unit externally with a dry cloth.
- Clean the grills with dry cloth.
- Check & ensure no vibration from the system.
- Clean the tube lights and its diffusers with dry cloth.
- Clean covers grills, air drag shield and frame with dry cloth.
- Start and run the machine in Auto/manual mode.
- Check the machine for any abnormal noise.
- After completion of the above procedure remove the “UNDER PREVENTIVE MAINTENANCE” status board from the machine and the respective electrical panel.
- Affix the Preventive Maintenance Status on machine as per Attachment – I of SOP/EN/003
- Update the status label of the machine after the completion of preventive maintenance and assembly respectively.
- After performing the preventive maintenance activity of machine, respective area supervisor shall check and note the details on respective Machine Operation & Cleaning Log Book.
- Engineering Supervisor/ above shall update the activity in respective formats of SOP for Calibration & Preventive Maintenance of Sampling &Dispensing Booth (SOP/EN/083).
REFERENCES:
In-House
- ABBREVIATIONS:
SOP : Standard Operating Procedure
Engg. : Engineering
- DISTRIBUTION LIST:
Engineering
Production
Quality Assurance
- HISTORY OF REVISION:
Revision No. | Effective Date | Reason for Revision |
Attachment – I
Preventive Maintenance Checklist of Sampling & Dispensing Booth
Area:
ID No: Date:
Frequency:
Sr. No. |
Particulars |
Status |
|
Check the electrical terminals of main supply and machine. | |
|
Check and ensure the free rotation of the blower motor shaft. Lubricate bearings, if required | |
|
Clean the impeller and its scrolls. | |
|
Clean the whole unit externally with a dry cloth. | |
|
Clean the grills with dry cloth. | |
|
Check & ensure no vibration from the system. | |
|
Clean the tube lights and its diffusers with dry cloth. | |
|
Start and run the machine in Auto/manual mode. | |
|
Check the machine for any abnormal noise.. |
Done By: Checked By: