- OBJECTIVE:
To describe a procedure for the preventive maintenance of Sticker Labeling Machines.
- SCOPE:
This SOP is applicable for preventive maintenance of Sticker Labeling machines
- RESPONSIBILITY:
Assistant Engineer/Above shall be responsible for implementation and compliance of this SOP.
- ACCOUNTABILITY:
Manager – Engineering / Manager – Production / Head – QA shall be accountable for implementation and compliance the procedure mentioned in this SOP.
- ATTACHMENT:
Preventive Maintenance Checklist of Sticker Labeling Machines -Attachment-I
- PROCEDURE:
- Preparation of preventive maintenance plan:
- Inform the concern person before starting preventive maintenance.
- Ensure that no activities are carried out in the respective machine.
- Ensure that the respective system electrical supply is switched “OFF”
- Before carrying out the preventive maintenance display status board as “UNDER PREVENTIVE MAINTENANCE” on the electrical panel and machine.
- FREQUENCY:
- Monthly
- Preparation of preventive maintenance plan:
- CHECKLIST:
- Check all electrical terminals of main supply and main panel for any loose wires.
- Check the machine for proper earthing.
- Check massage belt and pressing pad for any cut or damage, change if required.
- Check bottle and label sensors for proper working.
- Check and lubricate bearings and nut bolts for wear and tear where applicable.
- Start and run the machine in Auto/Manual mode.
- Check and observe the machine for its normal working.
- After completion of the above procedure remove the “UNDER PREVENTIVE MAINTENANCE” status board from the machine and the respective electrical panel.
- Affix the Preventive Maintenance Status on machine as per Attachment– I
- Update the status label of the machine after the completion of preventive maintenance.
- After performing the preventive maintenance activity of machine, respective area supervisor shall check and note the details on respective Equipment Sequential Log Book.
6.8 Junior Engineer/ above shall update the activity in respective formats of SOP for Maintenance of
Sticker Labeling machines (SOP/EN/074).
REFERENCES:
In-house
- ABBREVIATIONS:
SOP: Standard Operating Procedure
Engg.: Engineering
- DISTRIBUTION LIST:
Engineering
Production
Quality Assurance
10.0 HISTORY OF REVISION:
Version No. | Effective Date | Reason for Revision |
Attachment-I
Preventive Maintenance Checklist of Sticker Labeling Machines
Area:
ID No: Date:
Frequency:
Sr. No. |
Particulars |
Status |
|
Check all electrical terminals of main supply and main panel for any loose wires. | |
|
Check the machine for proper earthing. | |
|
Check massage belt and pressing pad for any cut or damage, change if required. | |
|
Check bottle and label sensors for proper working. | |
|
Check and lubricate bearings and nut bolts for wear and tear where applicable. | |
|
Start and run the machine in Auto/Manual mode. | |
|
Check and observe the machine for its normal working. |
Done By: Checked By: